East African Crude Oil Pipeline.

A transboundary crude oil pipeline connecting Uganda’s oil fields to the Tanzanian coast at Tanga — creating a strategic export route for Uganda’s petroleum resources.

EACOP route overview
UGANDA → TANZANIA
1,443 km Total pipeline length
296 km Route within Uganda
1,147 km Route within Tanzania
2 countries Uganda and Tanzania

A regional energy infrastructure project.

The EACOP starts in Hoima District in Uganda and terminates at Tanga port in Tanzania. Within Uganda, it traverses ten districts and seventy-one villages; in Tanzania, it traverses eight regions and twenty districts.

EACOP project route map
PROJECT ROUTE Hoima, Uganda → Tanga, Tanzania

Designed for Uganda’s crude.

The project combines specialised engineering with environmental and social considerations along its cross-border route.

01

Electrically heated

Because of the viscous and waxy nature of Uganda’s crude oil, the pipeline will need to be heated along the entire route.

02

Buried pipeline

The pipeline will be buried to minimise environmental and social impact, with some facilities above ground.

03

Route selection

The route was selected by the Government of Uganda as the least-cost and most robust option.

04

Compliance

The project is intended to comply with Ugandan and Tanzanian legislation and international requirements.

05

Marine export terminal

The Marine Export Storage Terminal and Load-Out Facility will be located north of Tanga port on the Chongoleani peninsula.

06

Cross-border infrastructure

The route links Uganda’s petroleum development to an Indian Ocean export point through Tanzania.

PROJECT DEVELOPMENT

Progress on EACOP.

A clear project chronology from agreement to ongoing engineering.

May 2017

The Inter-Governmental Agreement for the crude export pipeline was signed.

Oct 2020

Front-End Engineering Design was carried out and approved by the Petroleum Authority of Uganda.

Dec 2020

Environmental and Social Impact Assessment studies were approved and the certificate issued by NEMA.

Apr 2021

Host Government Agreements, Shareholders Agreement, and Tariff & Transportation Agreement were signed.

Ongoing

Detailed engineering activities, including optimisation and development of pipeline alignment sheets, are ongoing.

Explore related projects.

Explore more of UNOC’s project portfolio across upstream, midstream, and downstream activities.

MIDSTREAM

Kabalega Industrial Park

EXPLORE PROJECT →
MIDSTREAM

The Uganda Refinery Project

EXPLORE PROJECT →
UPSTREAM

Tilenga & Kingfisher Projects

EXPLORE UPSTREAM →
External project resource

Learn more about EACOP.

Visit the dedicated EACOP project website for more information.

VISIT PROJECT WEBSITE →